COMPLETED |
IN PROCESS |
| Pre-investment study |
|
|
| Technical – Economical Pre-feasibility study |
|
|
| Technical – Economical Feasibility study |
|
|
| Basic Engineering Design |
|
|
| Development of Detailed Engineering |
|
|
| Construction |
|
|
| Operation |
|
|
| Generation of Certified Emission Reductions (CERs) |
|
|
| |
|
|
| CO2 reduction (t/y) |
Not available yet |
| Total Installed Capacity (MW): |
0.5 (first 8 years. Soon it duplicates) |
| Plant power factor (MW): |
91% |
| Point of Entry to the Electric System: |
Network of low tension. SSEE San Felipe, V Region. |
| Annual Average Energy (KWH/YEAR): |
12.000 (first 8 years, Soon it duplicates) |
| Year of connection to the Electric System: |
2009 |